Aug 17, 2012

GABROVO MUNICIPALITY SIGNED A CONSTRUCTION CONTRACT PHASE 3 OF THE PROJECT FOR WATER CYCLE GABROVO

Gabrovo Municipality signed a construction contract for phase 3 of the project for construction and reconstruction of water supply and sewerage networks in the town. The project is funded by the Cohesion fund of the EU and by the state budget of Republic of Bulgaria through OP “Environment 2007 – 2013”.

Deputy Mayor of the Municipality Engineer Kliment Kunev and the manager of the implementing company affixed their signatures on the third constructional contract within the project.

Over the next two years, within this stage “Integrated project for water cycle of Gabrovo”, will be invested around 12 MBGN for new water supply infrastructure. By the middle of 2014, districts Radichevets, Yonkovoto, Lubovo, and Belenci and Lisec will have brand new ecological infrastructure.

With this the signed construction contracts are three totaling almost 50 MBGN.

The project for water cycle in Gabrovo is one of the three in implementation called “big projects” under OP “Environment 2007 – 2013”. As a result of its implementation around 32 km. sewerage will be reconstructed, around 14 km. new sewage will be built and 623 m. existing sewers will be rehabilitated. It will be built a water pressure tank, a new pump station will be constructed and other three will be repaired.