Priority axis 1: Water

Preparation of investment project in two phases - preliminary and technical designs, for construction of WWTP for treatment of the waste water of the Sunny Beach resort – the town of Nessebar

Category: Priority axis 1: Water

Amount: 2,074,106.70lv


Register number: 58131-110-110

Beneficiary type: Municipality

Beneficiary name: Nessebar

Project year: 2011

District: Nesebar

Region: Burgas


Goal

This project proposal provides for the design of treatment plant for the waste water of the town of Nessebar and the preparation and working out of all technical documentation necessary for the preparation of the construction work starting stage.


Acts

  • Preparing for the project implementation and for the forming of a team;
  • Selection of a contractor for developing of pre-investment researches;
  • Preparation of Environmental Impact Assessment and Compatibility Assessment;
  • Conduct public hearings in connection with EIA (Environmental Impact Assessment) and CO (Compatibility Assessment);
  • Selectionof expert consulting organization, which shall prepare documentation for awarding of public procurement contracts and work out of a project proposal for further application for funding under the OP “Environment”;
  • Preparation of tender dossier for awarding of a public procurement contract and selection of contractor for preparing of an investment project;
  • Development of DDP (Detailed Development Plan) and preliminary design;
  • Coordination of the DDP;
  • Working out of a detailed design;
  • Preparation of financial analyses, including analysis of costs and benefits;
  • Publicity and public awareness;
  • Audit of the project